Solutions
to Practice Problems – Chapter 6
1
a) Ignore
interest charges. Use the
depreciation that will be used for tax returns.
The working capital employed at the beginning of the last year will be
recovered at the end of the year.
Revenue
15,000
Manufacturing cost
- 8,000
Depreciation
- 500
Pre-tax income
6,500
Tax (@ 40%)
- 2,600
“N.I.”
3,900
Dep +
500
Recovery of W.C. + 1,500
Net cash flows 5,900
b)
Accelerated depreciation is higher in the early years of a project and lower in
the later years.
2. At the end of 4 years, the assets will be fully depreciated, and the entire salvage value will be taxable. This yields the following cashflows.
OCF
for project :
0
1
2
3
4
Revenue
-
400
660
672
693
Variable
Cost
-
(220)
(375)
(432)
(462)
Fixed
Cost
-
(55)
(65)
(75)
(85)
Depreciation
-
(166.65)
(222.25)
(74.05)
(37.05)
EBIT
-
(41.65)
(2.25)
90.95
108.95
Taxes
-
14.16
0.76
(30.92)
(37.04)
Net
Income
-
(27.49)
(1.49)
60.03
71.91
Depreciation
-
166.65
222.25
74.05
37.05
Increase
in W.C.
(5)
(3)
(0.6)
(0.4)
9
After-tax
Salvage Value
19.8
Operating
Cash Flow
(5)
136.16
220.16
133.68
137.76
Change
in Operating cashflow for existing business:
Increase
in EBIT
-
(10)
(8)
(8)
(8)
Increase
in Taxes
-
(3.4)
(2.7)
(2.7)
(2.7)
Increase
in OCF
-
(6.6)
(5.3)
(5.3)
(5.3)
Capital
Expenditure:
(500)
-
-
-
-
Net
Cash Flow:
-505
129.56
214.86
128.38 132.46
Note:
after-tax salvage value = 30,000 - .34*(30,000) = 19,800
3.
Since this company uses its tax depreciation in the income statement for
tax purposes, we don’t need to change depreciation.
Just ignore interest and take working capital into account. At time 4, you provide the additional working capital needed
for the last year ($100); at time 5 you recover the total working capital of
$1,900.
Year 4
Year 5
Revenue
32,000
35,000
Manufacturing cost
20,000
21,500
Depreciation 2,400
1,600
Pre-tax income
9,600
11,900
Tax (@ 40%)
3,840
4,760
N.I.
5,760
7,140
Dep
+
2,400
1,600
W.C.
- 100
+ 1,900
Net cash flows 8,060
10,640
4.
At time zero, the net cashflow will be –100,000 (capital investment)
– 2,00 (initial working capital) = -102,000.
The remaining cashflows are:
Year 1
Year 2
Year 3
Year 4
Revenue 23,000
24,500
26,250
28,300
Manufacturing cost
11,000
11,550
12,200
13,000
Depreciation
4,400
3,200
2,400
1,600
Pre-tax income
7,600
9,750
11,650
13,700
Tax (@ 40%)
3,040
3,900
4,660
5,480
N.I.
4,560
5,850
6,990
8,220
Depreciation 4,400
3,200
2,400
1,600
W.C.
- 100
- 150 -
150
+ 2,400
Net cashflows
8,860
8,900
9,240
12,220
5.
The project is an 8-year project (although the plant and equipment are
depreciated over 10 years). This
simply means that when the project is terminated at the end of 8 years, the
plant and equipment will not be fully depreciated.
The capital gain on the sale will have to be computed using the book
value at time 8:
Accumulated depreciation for 8 years = 960
Book value at time 8 = 1200 – 960 = 240
Capital gain = 400 – 240 = 160
Tax @ 35% = 56
The net cashflows that would be obtained from renting the warehouse if
it wasn’t used for the project must be charged to the project too, since it is
an opportunity cost.
The cashflow at time zero will consist of the capital investment of
$1.2m and the initial working capital.
|
Item |
t
= 0 |
t
= 1 |
t
= 2 |
t
= 3 |
t
= 4 |
t
= 5 |
t
= 6 |
t
= 7 |
t
= 8 |
|
|
|
|
|
|
|
|
|
|
|
|
Sales |
4200.0 |
4410.0 |
4630.5 |
4862.0 |
5105.1 |
5360.4 |
5628.4 |
5909.8 |
|
|
Mfg. Cost |
|
3780.0 |
3969.0 |
4167.5 |
4375.8 |
4594.6 |
4824.3 |
5065.6 |
5318.8 |
|
Depreciation |
|
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
|
EBT |
|
300.0 |
321.0 |
343.1 |
366.2 |
390.5 |
416.0 |
442.8 |
471.0 |
|
Taxes |
|
105.0 |
112.4 |
120.1 |
128.2 |
136.7 |
145.6 |
155.0 |
164.8 |
|
Net Income |
|
195.0 |
208.6 |
223.0 |
238.2 |
253.8 |
270.4 |
287.8 |
306.1 |
|
Depreciation |
|
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
120.0 |
|
OCF |
|
315.0 |
328.7 |
343.0 |
358.0 |
373.8 |
390.4 |
407.8 |
426.1 |
|
|
|
|
|
|
|
|
|
|
|
|
Initial W.C. |
-350.0 |
|
|
|
|
|
|
|
|
|
Inc. in W.C. |
|
-70.0 |
-21.0 |
-22.1 |
-23.2 |
-24.3 |
-25.5 |
-26.8 |
|
|
Rcvry of W.C. |
|
|
|
|
|
|
|
|
562.8 |
|
|
|
|
|
|
|
|
|
|
|
|
Rent (after tax) |
|
-65.0 |
-67.6 |
-70.3 |
-73.1 |
-76.0 |
-79.1 |
-82.2 |
-85.5 |
|
|
|
|
|
|
|
|
|
|
|
|
Capital Inv. |
-1200.0 |
|
|
|
|
|
|
|
|
|
Sale of Plant |
|
|
|
|
|
|
|
|
400.0 |
|
Tax on Sale |
|
|
|
|
|
|
|
|
56.0 |
|
|
|
|
|
|
|
|
|
|
|
|
Net Cashflow |
-1550.0 |
180.0 |
240.1 |
250.6 |
261.8 |
273.5 |
285.8 |
298.8 |
1247.4 |
6)
Machine A
NPV
= 3600/1.15 + 3600/1.152 + … 3600/1.156 - 8,000 =
13,624.14 - 8,000 = 5,624.14
EAC
is given by
EAC/1.15 + EAC/1.152 + … EAC/1.156
= 5,624.14
Solving,
EACA = 1,486.10
=>
Using machine A is like generating a cash inflow of 1,486.10 each year.
Machine B
NPV
= 5700/1.15 + … 5700/1.158
- 13,000 = 25,577.73 – 13,000 = 12,577.73
EAC
is given by
EAC/1.15 + EAC/1.152 + … EAC/1.158
= 12,577.73
Solving,
EACB = 2,802.95
=>
Using machine B is like generating a cash inflow of 2,802.95 each year.
=>
Choose machine B
7
a) Machine
A
NPV
= 15,000/1.15 + … 15,000/1.154 - 36,000 = 42,824.68 - 36,000 =
6,824.68
EAC
is given by
EAC/1.15 + … EAC/1.154
= 6,824.68
Solving,
EACA = 2,390.45
=>
Using machine A is like generating a cash inflow of 2,390.45 each year.
Machine B
NPV
= 16,000/1.15 + … 16,000/1.156
- 52,000 = 60,551.72 - 52,000 = 8,551.72
EAC
is given by
EAC/1.15 + … EAC/1.156
= 8,551.72
Solving,
EACB = 2,259.68
=>
Using machine B is like generating a cash inflow of 2,259.68 each year.
=>
Choose machine A
b)
Trying to use IRR, we would proceed as follows:
Using
a financial calculator, IRRA = 24.10%, and IRRB = 20.93%
The
incremental cashflows for B - A are:
0
1 2
3
4
5
6
-16,000 1,000 1,000
1,000 1,000 16,000
16,000
These
are conventional cashflows; IRR turns out to be 17.41% which is greater than the
required return of 15%. This seems
to say that the incremental project B-A is worth taking => choose project B.
The
reason why we get the wrong answer is that we are comparing non-comparable
alternatives. Project B is looking
better because with B we are including the benefit of 6 year’s production
whereas with A we are including the benefit of only 4 year’s production. Just
like the NPV method, the IRR method can only be applied to cash flows over a
common production horizon.
8.
First compute Equivalent Annual Cashflow for the new machine:
NPV
= 4600/1.12 + … 4600/1.128
- 20,000 = 22,851.14 - 20,000 = 2,851.14
EAC
is given by
EAC/1.12 + … EAC/1.128
= 2,851.14
Solving,
EAC = 573.94
The
cashflows for the different replacement alternatives are then:
Time C0 C1
C2 C3
0
600
574 574 574 .
. .
1
600
500 574 574 .
. .
2
600
500 400 574
. . .
Cashflows
beyond time 2 are 573.94 each year in each case, and can be ignored.
It
is clear that the old machine should be replaced right away (at time 0).
It generates only $500 the first year, whereas once you put in a new
machine it is like getting $574 forever.
9.
First compute Equivalent Annual Cashflow for the new machine:
NPV
= 5000/1.08 + … 5000/1.086
- 9,000 = 23,114.40 - 9,000 = 14,114.40
EAC
is given by
EAC/1.08 + … EAC/1.086
= 14,114.40
Solving,
EAC = 3053.16
Assume
the salvage values given are after-tax values (since no tax rate is given).
If you replace at time 0, you will get the cashflow of 3,000 today plus
the salvage value of 1,500, so the cashflows will be 4500 today and then 3053
forever. If you replace at time 1,
you will get 3,000 at time 0 followed by 2,000 + 1,000 at time 1 and then 3053
forever. If you replace at time 2, you will get 3,000 at time 0, 2,000 at time 1
followed by 1200 + 500 at time 2 and then 3053 forever.
If you replace at time 3, you will get 3,000 at time 0, 2,000 at time 1,
1200 at time 2, 500 at time 3 and then 3053 forever.
So
the cashflows are:
Time
C0 C1
C2
C3
C4
C5
0
4500 3053
3053 3053
3053 3053
. . .
1
3000 3000
3053 3053
3053 3053
. . .
2
3000 2000
1700 3053
3053 3053
. . .
3
3000 2000
1200 500
3053 3053
. . .
Cashflows
beyond time 3 are 3053.16 each year in all four cases, and can be ignored.
Clearly, replacing at time 2 is better than replacing at time 3; replacing at time 1 is better than replacing at time 2, and replacing at time 0 is better than replacing at time 1. So the machine should be replaced right away.
10.
First compute Equivalent Annual Cost for the new circuits.
PV of costs = 1200 + 200/1.153 + 320/1.154 + 545/1.155
= 1785.45
=>
EAC/1.15 + EAC/1.152 + … EAC/1.155
= 1785.45
Solving, EAC = 532.62
Since the existing circuits will last only for 3 years, they must be
replaced at time 0, 1, 2 or 3. Using
the equivalent annual cashflows for the new circuits instead of the original
cashflows, the equivalent cashflows from different replacement options are as
follows:
Time
C0 C1
C2
C3
C4
C5
0
0
533 533 533
533 533
. . .
1
0
350 533
533 533
533 . . .
2
0
350 600
533 533 533
. . .
3
0
350 600
460 533 533
. . .
Cashflows beyond time 5 are 533 each year in all four cases (as new
circuits are replaced by new circuits). We
can ignore cashflows beyond time 3, since they are equal in all four cases.
Clearly, replacing at 1 is cheaper than replacing at time 0 or 2.
But we cannot choose between replacing at 1 or 3 just by looking at the
cashflows. So compare PV2
of the time 2 and 3 cashflows:
PV2(if replace at 1) = 533 + 533/1.15 = 996.48
PV2(if replace at 3) = 600 + 460/1.15 = 1000
=> 1 has the lower PV of
costs, and the circuits should be replaced at time 1
The
assumptions made here are the standard assumptions that must be made whenever we
use EAC:
|
Robot E. Robot wants to live indefinitely | |
|
Once he puts in new brain circuits, he will keep replacing them with new ones every 5 years | |
| Cashflows for the new circuits (both initial cost and maintenance expenses) remain constant at each replacement |
11.
Compute the E(R) from waiting or the PV at time 0 of the future values:
Time
0
Time 1 Time 2
Time 3
Time 4
$8.99
$10.75
$12.50
$13.75
$14.99
E(R)
19.58% 16.28%
10%
9.02%
PV0(FVt)
$ 9.77
$10.33
$10.33
$10.24
You do want to wait for the first two
years. Whether you wait for the
third year or not doesn’t matter. The
expected return equals the required return, so it’s a zero NPV investment.
(That’s reflected in PV0 being equal at time 2 and
time 3.) A zero NPV investment has
no effect on s/h wealth, so stockholders don’t care whether you wait for the
third year or not. Thus, the wine
can be sold at either time 2 or time 3.
12
a) You can compute either the E(R) from waiting, or the PV of the future
NPVs:
Time
t
0
1
2
3 4
NPVt
2,400
2,850
3,225
3,515 3,725
E(R)
18.75% 13.16%
8.99%
5.97%
PV0NPVt
2,567.57 2,617.48
2,570.14
2,453.77
Either way the project should be taken at time 2. The expected return from waiting > required return for the first two years, so you wait and take it at the end of two years. Or taking it at time 2 produces the future NPV with the highest PV today.
b) The asking price for the project would have to be the PV today of the future NPV you get, when you take it at time 2: 2,617.48.
13.
First we need to figure out what’s the best time to cut the trees. Then the price we should ask for today is the PV today of the
future NPV from the best choice.
Putting
on our thinking cap before we start will reduce the number of tedious
computations we need to make. The amount we receive consists of the value of the timber +
the value of the land. As long as
this combined value increases faster than the required return of 9%, we should
wait. Up to time 8, the value of
the timber increases more than 9%, the value of the land increases by 4% =>
computations are necessary to see
whether the combined value increase by more than 9% or less than 9% each year.
But
after time 8, the value of the timber increases by 8.16% each year (1.04*1.04
– 1). Both timber and land values
increase less than 9%, so the combined value increases less than 9%.
Thus, we only need to make computations for time 1 through 8:
|
Time |
#
of cords |
Price/cord |
#
of |
Price/acre |
Total |
E(R)
from |
PV
of |
|
|
|
|
acres |
|
Value |
Waiting |
future
NPV |
|
0 |
1000.00 |
40.00 |
500 |
100.00 |
90,000 |
|
90,000 |
|
1 |
1160.00 |
41.60 |
500 |
104.00 |
100,256 |
11.40% |
91,978 |
|
2 |
1345.60 |
43.26 |
500 |
108.16 |
112,296 |
12.01% |
94,517 |
|
3 |
1560.90 |
44.99 |
500 |
112.49 |
126,475 |
12.63% |
97,662 |
|
4 |
1810.64 |
46.79 |
500 |
116.99 |
143,221 |
13.24% |
101,461 |
|
5 |
2009.81 |
48.67 |
500 |
121.67 |
158,642 |
10.77% |
103,107 |
|
6 |
2230.89 |
50.61 |
500 |
126.53 |
176,177 |
11.05% |
105,049 |
|
7 |
2476.29 |
52.64 |
500 |
131.59 |
196,142 |
11.33% |
107,296 |
|
8 |
2748.68 |
54.74 |
500 |
136.86 |
218,899 |
11.60% |
109,858 |
Clearly,
the trees should be cut at time 8. The
fair value of the property today is then $109,858.
The offer of $140,000 should be accepted forthwith!
14. The
total output per machine is 2,500 + 1,000 = 3,500 gallons
If
you keep the old machines:
Annual
operating cost = 2*3,500*1.50 = 10,500
PV
of operating costs = 10,500/0.05 = 210,000
If
you replace both machines:
Initial
investment = 2*1,500 = 3,000
Annual
operating cost = 2*3,500*1 = 7,000
PV
of costs = 2*30,000 + 7,000/0.05 = 200,000
Replace
just one machine:
The new machine is cheaper per unit ($1 instead of $1.50). In the fall/winter, you’ll use only the new machine to get the 2000 gallons you need. In spring/summer, you’ll use both machines, to get the 5000 gallons you need.
Output
of new machine = 4,500; output of old machine = 2,500
Initial
investment = 30,000
Annual
operating cost = 4,500*1 + 2,500*1.5 = 8,250
PV
of costs = 30,000 + 8,250/0.05 = 195,000
=>
It’s best to replace just one machine. Replacing
the second machine just to produce 2,500 gallons is not cost effective.
15.
The
total output per machine is 6,000 + 3,600 = 9,600 shovels
If
you keep the old machines:
Annual
operating cost = 2*9,600*4 = 76,800
PV
of operating costs = 76,800/0.05 = 1,536,000
If
you replace both machines:
Initial
investment = 2*100,000 = 200,000
Annual
operating cost = 2*9,600*3.25 = 62,400
PV
of costs = 200,000 + 62,400/0.05 = 1,448,000
Replace
just one machine:
The new machine is cheaper per unit ($3.25 instead of $4). In the spring/summer you’ll use only the new machine at 100% capacity to produce 6000 shovels, and the old machine just to produce the remaining 1,200 shovels you need. In fall/winter, you’ll use both machines, to produce 6000 shovels each.
Output
of new machine = 12,000; output of old machine = 7,200
Initial
investment = 100,000
Annual
operating cost = 12,000*3.25 + 7,200*4 = 67,800
PV
of costs = 100,000 + 67,800/0.05 = 1,456,000
=>
This time it’s best to replace both machines.
Replacing the second machine to produce 7,200
is cost effective.